The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV)

B) Earned Value(EV) divided by Planned Value (PV)

C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV))

D) Earned Value (EV) minus Planned Value (PV)

View Answer
Option – B.