The price that you charge for your project is

A) equal to the cost estimate plus a fixed percentage.

B) essentially the same as the cost estimate.

C) typically 1.5 – 2.5 times the cost estimate in order to account for corporate overhead costs

D) a business decision that considers the cost estimate together with other factors.

View Answer
Option – D.