Construction Planning & Management MCQ Questions Answers – Civil Engineering
Construction planning and management play a pivotal role in the successful execution of construction projects. Whether it’s a small residential building or a large-scale infrastructure project, proper planning and effective management are essential for timely completion, cost control, and quality assurance. In this article, we will explore some multiple-choice questions (MCQs) related to construction planning and management, along with their answers, to enhance your understanding of this critical aspect of the construction industry.
1) Mile stone chart is an improvement over
a) Bar chart
b) CPM scheduling
c) PERT scheduling
d) All the above
2) Which of the following is a weakness of bar chart ?
a) interdependencies of activities
b) project progress
c) uncertainties
d) all of the above
3) The process of inspiring the subordinates to do a work or achieve an objective is called as
a) Management
b) Supervision
c) Motivation
d) Communication
4) Which of the following does not represent an activity ?
a) site located
b) Foundation is being dug
c) the office area is being cleaned
d) The invitations are being sent
5) In a bar chart the vertical axis represents
a) Time
b) Types of activities
c) Number of labours
d) Various avtivities of the project
6)Grader is used mainly for
Trimming and finishing
Shaping and trimming
Finishing and shaping
Finishing, shaping and trimming
7) A critical path has
a) zero slack
b) minimum slack
c) maximum slack
d) infinite slack
8) Which of the following earth moving machines has the shortest cycle time ?
a) Drag line
b) Hoe
c) Clam shell
d) Dipper shovel
9) The independent float affects only
a) preceding activities
b) succeeding activities
c) the particular activity involved
d) None of the above
10) Probability of finishing of a project earlier than expected time is
a) 100%
b) less than 50%
c) more than 50%
d) None of these